JSEA RM-09/SCS Health & Safety Management System

Use of Main-Contractor-Provided Scaffold

Responsive Maintenance · Rev 1.0 · Approved master — controlled document

HIGH

Task steps, hazards and controls

Swipe or step through on mobile

Step 1 of 4

Verify status and handover before first use

Hazards

Use of incomplete, unhandover or unsafe scaffold

Critical controls

Check the scaffold tag / handover certificate and its date, confirm it is suitable for the intended work and duration, confirm correct access is provided

Critical controls

  • Scaffold confirmed suitable for the work, with correct access and current handover / tag status before use
  • No alteration, removal or addition of scaffold components by SCS personnel
  • Loading limits observed and platforms kept clear; incomplete or damaged scaffold is not used and is escalated to the Main Contractor