JSEA RM-03/SCS Health & Safety Management System

Interior Plaster Repairs & Wall Patching

Responsive Maintenance · Rev 1.0 · Approved master — controlled document

MEDIUM

Task steps, hazards and controls

Swipe or step through on mobile

Step 1 of 4

Assess the damaged area and existing linings

Hazards

Suspect asbestos or hazardous linings, concealed services, structural damage

Critical controls

Apply JSEA RM-15, check property and asbestos information, use a detector before cutting, escalate structural damage to the Main Contractor

Critical controls

  • Work platform or ladder assessed as suitable before any above-shoulder work
  • Compound mixing carried out with P2 RPE and eye protection
  • Asbestos / unknown material hold point applied before disturbing existing linings

Minimum PPE

Safety footwearEye protectionNitrile glovesP2 dust mask for mixing and sandingKnee protection