Specialised Contracting Solutions
3
JSEA 21/SCS Health & Safety Management System

Asbestos-Containing Materials (ACM) Encounter Protocol

Critical Risk · Rev 1.0 · Approved master — controlled document

CRITICAL

Task steps, hazards and controls

Swipe or step through on mobile

Step 1 of 3

Recognise suspect material

Hazards

Asbestos fibre release

Critical controls

Stop work, leave material undisturbed, no cutting or sanding

Critical controls

  • STOP WORK immediately on suspicion of ACM
  • Do not disturb — isolate and notify H&S Manager
  • Licensed asbestos assessor engaged before resuming

Minimum PPE

P3 RPE (evacuation only)Disposable coveralls

Sign-on register

0 signature(s) this session

No workers signed on yet in this session.